Cyclists and drivers on the Stanningley Bypass between Leeds and Bradford face four weeks of contraflow systems and overnight closures from Monday, 27 July, as part of the £44.179 million Dawsons Corner and Stanningley Bypass scheme.
The works run from Monday, 27 July to Tuesday, 26 August 2026. A contraflow system — where traffic travels in the opposite direction on part of the carriageway — will be in place for the duration, with a 30mph speed limit 24 hours a day, seven days a week.
The contraflow runs southbound from 8 pm on Monday, 27 July to Monday, 10 August, then switches to northbound from 5 am on Tuesday, 11 August to Friday, 21 August. Partial closures will be in place during set-up and switchover periods, with signed local diversions.
Full overnight closures on the Stanningley Bypass near Swinnow Lane are scheduled for resurfacing on Monday, 24 August (8 pm to 5 am) and Tuesday, 25 August (8 pm to 5 am). Additional full overnight closures are required to install, switch and remove the contraflow on the following dates: Monday, 27 July (contraflow installation, southbound), Tuesday, 28 July (contingency date), Monday, 10 August (contraflow switch) and Friday, 21 August (removal of contraflow).
The works have been timed to coincide with the school summer holidays, when traffic levels are typically lower. Delays are still expected, particularly at peak times. Anyone travelling on the A647 or A6120 between Leeds and Bradford from 27 July is advised to allow extra time, follow signed diversions and consider alternative routes.
When complete, the scheme will reduce congestion and delays, improve bus journey time reliability, provide safer crossing facilities for pedestrians and cyclists, and support economic growth across West Yorkshire. The work builds on over 140 carriageway repairs already carried out along the Stanningley Bypass over the past four summers as part of the council’s annual maintenance programme.
Councillor Peter Carlill, Leeds City Council’s executive member for transport and planning, said: “We would like to thank people for their continued patience as work takes place at Dawsons Corner.”
He added: “Good progress is being made, and the scheme remains on track for completion early next year. From Monday 27 July, anyone travelling between Leeds and Bradford on the A647 or using the A6120 should allow extra time, follow signed diversions and consider alternative routes where possible.”