Bradford Council has begun construction on the Thornton Road Improvements Project, delivering a segregated cycle route, safer crossings and junction upgrades along Thornton Road between Spring Head Road and Girlington Road.
The project brings together the West Bradford Cycle Superhighway Phase 2 and the Four Lane Ends Corridor Improvement Scheme alongside wider improvements to the corridor. Bradford Council is delivering it in partnership with the West Yorkshire Combined Authority, funded by the UK Government through the Combined Authority. The funding is ringfenced for sustainable transport infrastructure and cannot be used for other council services. Most works are expected to be complete by spring 2028, with final planting in early summer 2028, subject to weather and construction conditions.
When complete, the scheme will deliver a high-quality, largely segregated cycle route connecting to the existing West Bradford Cycle Superhighway, new and upgraded crossings, and junction improvements including increased capacity at Four Lane Ends and safer side-road junctions. It will also provide upgraded and repositioned bus stops, changes to some parking and loading areas, new trees, planting and landscaping, and new lighting, drainage, road markings and resurfacing.
During the first four weeks, work focuses on the stretch between Thornton and Fairweather Green. This includes tree pruning, temporary road markings and safety fencing, changes to some central traffic islands, early kerb and drainage work, a gas diversion near Beckfoot Thornton School and completion of a temporary site compound off Rhodesway. No tree felling will take place during the initial pruning phase.
Construction will move through six planned areas along Thornton Road, including at Four Lane Ends, with some work potentially running in more than one area simultaneously. Most work takes place during weekday hours between 7 am and 5.30 pm, with some weekend or night work required for surfacing and road markings. Thornton Road will remain open wherever possible, with narrowed lanes and temporary traffic signals expected to cause some delays.
Bus services are expected to continue throughout, though some stops may be temporarily relocated. Safe routes for people walking, cycling or using mobility aids will be maintained throughout construction, with signed diversions where necessary. 24-hour access to Fairweather Green Fire Station will be maintained at all times. Residents and businesses will receive advance notice of significant work affecting their area wherever practicable.
Councillor Andrew Judson, Bradford Council’s Executive Member for Economy, Regeneration and Planning, said: “The scheme will make it easier and safer for people to get around, whether they are walking, cycling, using mobility aids or travelling by bus, while also improving the overall environment along the corridor. Every effort will be made to minimise disruption, keep people informed throughout the works and maintain access wherever it is safe to do so.”
Further information is at www.yourvoice.westyorks-ca.gov.uk/thorntonroad.